Abstract:It is inevitable to cross desert for the transmission line project. Suggestions on route selection in the desert section of one transmission line project in Northwest China are put forward in terms of pole-tower location, foundation form selection, wind break and sand fixation. Some countermeasures for preventing and controlling wind-sand hazards are proposed as well. The methods and measures are proved to be reasonable, and the lines also run well.
宋国新. 输电工程沙漠段危害及对策研究[J]. 地质与资源, 2018, 27(6): 579-581.
SONG Guo-xin. STUDY ON THE HARM OF DESERT SECTION ON TRANSMISSION PROJECTS AND COUNTERMEASURES. GEOLOGY AND RESOURCES, 2018, 27(6): 579-581.